Question: Gantt table provided below that question is referring to question I am needing assistance on below thank you! Status Report Assignment In our previous assignments

Gantt table provided below that question is

Gantt table provided below that question is

Gantt table provided below that question is referring to

Gantt table provided below that question is

question I am needing assistance on below

Gantt table provided below that question is

thank you!

Status Report Assignment In our previous assignments we started with our project while it was in its initiation phase and we completed a project charter, we then moved on to the project's planning phase and completed a project plan. Now our dream house project has moved on to its execution phase, in this phase, the house construction is well underway and (as project managers) We are concemed about monitoring and controlling the project. One of the main elements of monitoring a project is to be able to understand and report on its progress, this is often reported on using a performance report. For this assignment you can assume that work on the dream house is underway, and again we take on the role of a project manager to create a performance report for the project - our goal is to determine if the project is on track or not. The 'Work Performance Report, also known as the project 'status report or "progress report, is an essential tool for a project manager to communicate a snapshot of the project's status to the stakeholders in a concise, clear format. The original schedule for the project was as follows: Week End Week End Week 3 Week End Week 4 Week End Week 5 Week End Week 1 1 2 3 4 5 Week 2 167 B 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 1.1.1 Task A 1.1.2 Task B 1.1.3 Task c 1.2.1 Task D 1.2.2 Task E 1.2.3 Task F 1.3.1 Task 1.3.2 TSKH 1.3.3 Taski 1.4.1 Task) 1.1.2 TAKK 114.3 TL 1.5.1 Task M 1.5.2 TEN 1.5. Tako 1.6.1 Inspection Milestona 1 ON Milestone #2 On day 15 the following project status related notes were recorded Week 1 Week End Week 2 Week End Week 3 Week End Week 4 Week End 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 1 2 3 4 1.1.1 Task A 11 2 Task B 1.1.3 Task c 121 Task D Week Week 5 End 21 22 23 24 25 Planned Schedule Actual Status 1.2.2 Task E 1.2.3 Task F 1.3.1 Task G 1.3.2 Task H 1.3.3 Task ! 14.1 Task 1 1.4.2 Task K 1.4.3 Task L 1.5.1 Task M 1.5.2 Task N! 153 Task o 1.6.2 Milestone #1 1.6.1 Inspection 1.6.3 Milestone #2 You are to use this supplied project performance related information in preparing a status report for this project. The writing guide below details what sections, and what content, need to be included in your status report. 5) Eamed Value Analysis (See PMBOK Table 7-1): For your reports you must utilize the project's current status information presented earlier in this assignment to demonstrate your knowledge of eamed value analysis. The easiest way to complete this assignment is to copy the following table into Excel and set up Excel formulas that you will need to calculate each required value. Earned Value Analysis Table: Complete the missing information for the project, assuming that it is the end of day 15 on the project. Please refer to above Gantt charts for the task planned and completed status. WBS Item Budgeted Planned Planned Actual Status Earned Cost Schedule Value Status Value Cost Completed Value Variance Variance 1.1 Landscape 1.1.1 Task A $3,000 $1,000 1.1.2 Task B $4,500 $1,500 1.1.3 Task C $15,000 $6,000 1.2 House Structure 1.2.1 Task D $1,500 $400 1.2.2 Task E $7,000 0 1.2.3 Task F $2,000 $1,500 1.3 Inside Work 1.3.1 Task G $3,000 $2,800 1.3.2 Task H $9.000 $9,000 1.3.3 Task! $1,000 0 1.4 Infrastructure 1.4.1 Task J $6.000 $2,000 1.4.2 Task K $8,000 $8,000 1.4.3 Task L $1,000 n/a 1.5 Management 1.5.1 Task M $3,000 $2,800 1.5.2 Task N $1,000 $1.100 1.5.3 Task o $8,000 0 1.6 Other 1.6.1 Inspection $1,000 $1000 1.6.2 Milestone $0 0 Your earned value analysis section is also to include the following information

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!