Question: Earned Value Given the following budgeted and accomplished work as of week 1 6 , calculate earned value for each activity, and for the project.

Earned Value
Given the following budgeted and accomplished work as of week 16, calculate earned value for each activity, and for the project. There is a penalty of $500,000 if the project takes over 25 weeks.
Actual costs are Actual weeks times Pay rate.
Calculate efficiency based on dollars for each activity and overall project efficiency at this stage.
Activity Budget Actual % complete Pay rate Earned value
Grading 6 weeks 5 weeks 100 $40,000/week
Prepare base 3 weeks 4 weeks 100 $20,000/week
Culverts 8 weeks 10 weeks 100 $30,000/week
Bridge 20 weeks 16 weeks 50 $80,000/week
Surface 3 weeks 1 week 33 $100,000/week
Painting 1 week 0 $55,000/week
Budget estimates are obtained from pre-bid estimates.
Actual expenses are obtained from accounting as moneys are spent.
The sequential relationships are:
Grading precedes Prepare base and Culverts
Prepare base and Culverts precedes Surface
Bridge and Surface precede Painting
Some overlap of activities is present, as you dont have to have 100% completion of a predecessor to start some activities. Predecessor relationships really arent needed for the accounting side of the assignment.
Give a short analysis of current status by activity and for the overall project.Earned Value
Given the following budgeted and accomplished work as of week 16, calculate earned value for each activity, and for the project. There is a penalty of $500,000 if the project takes over 25 weeks.
Actual costs are Actual weeks times Pay rate.
Calculate efficiency based on dollars for each activity and overall project efficiency at this stage.
\table[[Activity,Budget,Actual,% complete,Pay rate,\table[[Earned],[value]]],[Grading,6 weeks,5 weeks,100,$40,000/ week,],[\table[[Prepare],[base]],3 weeks,4 weeks,100,$20,000/ week,],[Culverts,8 weeks,10 weeks,100,$30,000/ week,],[Bridge,20 weeks,16 weeks,50,$80,000/ week,],[Surface,3 weeks,1 week,33,$100,000/ week,],[Painting,1 week,0,,$55,000/ week,]]
Budget estimates are obtained from pre-bid estimates.
Actual expenses are obtained from accounting as moneys are spent.
The sequential relationships are:
Grading precedes Prepare base and Culverts
Prepare base and Culverts precedes Surface
Bridge and Surface precede Painting
Some overlap of activities is present, as you don't have to have 100% completion of a predecessor to start some activities. Predecessor relationships really aren't needed for the accounting side of the assignment.
Give a short analysis of current status by activity and for the overall project.
 Earned Value Given the following budgeted and accomplished work as of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!