Question: Earned Value Management Exercise Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of
Earned Value Management Exercise
Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of $1500 per section.
Her plan was to complete 2 sections in week one.
You, as the PM check the financials at the end of week one and you see that Jane has spent $1800 and has completed 1 section.
How is Jane doing on this project as determined by Earned Value analysis?
{describe how Jane is doing here}
Calculate the following:
PV = {put answer here}
AC = {put answer here}
EV = {put answer here}
CV = {put answer here}
SV = {put answer here}
CPI = {put answer here}
SPI = {put answer here}
BAC = {put answer here}
EAC = {put answer here}
VAC = {put answer here}
ETC = {put answer here}
TCPI = {put answer here}
Step by Step Solution
There are 3 Steps involved in it