Question: Earned Value Management Exercise Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of

Earned Value Management Exercise

  • Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of $1500 per section.
  • Her plan was to complete 2 sections in week one.
  • You, as the PM check the financials at the end of week one and you see that Jane has spent $1800 and has completed 1 section.
  • How is Jane doing on this project as determined by Earned Value analysis?

{describe how Jane is doing here}

Calculate the following:

  • PV = {put answer here}
  • AC = {put answer here}
  • EV = {put answer here}
  • CV = {put answer here}
  • SV = {put answer here}
  • CPI = {put answer here}
  • SPI = {put answer here}
  • BAC = {put answer here}
  • EAC = {put answer here}
  • VAC = {put answer here}
  • ETC = {put answer here}
  • TCPI = {put answer here}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!