Question: Earned Value Management - Given the following information for a partially-completed project with an estimated total duration of one year, answer the following questions. Recall

 Earned Value Management - Given the following information for a partially-completed

Earned Value Management - Given the following information for a partially-completed project with an estimated total duration of one year, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. To receive credit, sh your we for all answers. PV=$77,000 EV=$67,000 AC=$51,000 BAC=$125,000 1. What is the cost variance (CV), schedule variance (SV), cost performance index (CPI), and schedule performance index (SPI) for this project? 2. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? 3. Use the CPI to calculate the estimate at completion (EAC) for this project. 4. EXTRA CREDIT: Use the SPI to estimate how long it will take to finish this project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!