Question: Earned Value minus planned vbalue is A . Schedule variance B . Cost performance index C . Cost variance D . Schedule performance index At

Earned Value minus planned vbalue is
A. Schedule variance
B. Cost performance index
C. Cost variance
D. Schedule performance index
At the end of the project, the schedule variance is equal to
A. earned value
B. one
C. planned value
D. zero
The method of measurement used for support type activities that doesn't produce definitive end products that can be delivered or measured objectively
A. fixed formula
B. level of effort
C. Weighted milestone
D. Percentage complete
E. apportioned effort
The Authorized budget assigned to scheduled work
A. percentage complete
B. Planned value
C. Cost variance
D. Undistributed budget
Your cost analyst has calculated that your project has an estimate at completion of $150,000. Given that you know that the project budget is $125,000, what can you infer about the project's cost performance index results up to this point?
A. Cost performance index is below 1
B. there is not sufficient information to infer
C. Cost performance index is 1
D. Cost performance index is above 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!