Question: Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 Pour foundation April 1 $50,000 May
Earned-value analysis. A project budget calls for the following expenditures:
| Task | Date | Budgeted Amount |
| Build forms | April 1 | $10,000 |
| Pour foundation | April 1 | $50,000 |
| May 1 | $100,000 | |
| Frame walls | May 1 | $30,000 |
| June 1 | $30,000 | |
| Remaining tasks | July 1 and beyond | $500,000 |
Define each term in your own words, calculate these values for the above project, and show your work:
- SV as of May 1.
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
- Estimate at completion (EAC)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
