Problem 16-12(Static)
A shoe repair operation uses a two-step sequence that all jobs in a certain category follow. All jobs can be split in half at both stations. For the group of jobs listed:
JOB TIMES (minutes)
A B C D E
Workstation A 2718702615
Workstation B 4533302410
Click here for the Excel Data File
a. Find the sequence that will minimize total completion time.
b. Determine the amount of idle time for workstation B.