Question: Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the project's MIRR? WACC: 8.00% Year 0
Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the project's MIRR?
WACC: 8.00%
| Year | 0 | 1 | 2 | 3 |
| Cash flows | -$1,000 | $425 | $425 | $425 |
Please show the how and why in your calculations. Thanks!