Question: Eight jobs are to be processed through a single machine. The processing times and due dates are given here. Determine the sequence in which these

Eight jobs are to be processed through a single machine. The processing times and due dates are given here.

Eight jobs are to be processed through a single

Determine the sequence in which these jobs should be done in order to minimize the maximum lateness subject to the precedence restrictions.

a. 2 1 4 6 5 3 7 8

b. 2 1 4 5 6 3 7 8

c. 2 4 1 6 5 7 3 8

d. 2 1 4 6 5 3 8 7

Determine the maximum lateness subject to the precedence restrictions:

a. 2

b. 0

c. 3

d. 1

Job 1 2 3 4 5 6 7 8 Processing time N 3 3 2 1 4 3 2 2 Due date 5 4 13 6 12 10 15 19

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock