Question: Can you help me to solving for this question? Question 1) Eight jobs are to be processed through a single machine. The processing times and

Can you help me to solving for this question?Can you help me to solving for this question?

Question 1) Eight jobs are to be processed through a single machine. The processing times and due dates are given here. Job Processing time Due date U 2 3 4 3 2 13 4 1 6 5 4 12 6 3 10 7 2 15 00 NO Furthermore, assume that the following precedence relationships must be satisfied: Job Immediately preceeded by 1 2 3 6 4 1 5 6 2 7 4 8 7 Determine the sequence in which these jobs should be done in order to minimize the maximum lateness subject to the precedence restrictions