Question: Electralloy Ccorporation data for last month was: queue time was 7 . 8 days, inspection time was 0 . 3 day, process time was 1
Electralloy Ccorporation data for last month was: queue time was days, inspection time was day, process time was days, wait time was days, and move time was day.
Required:
a Compute the throughput time.
b Compute the manufacturing cycle efficiency MCE
c What percentage of the production time is spent in nonvalueadded activities?
d Compute the delivery cycle time.