Question: Electralloy Ccorporation data for last month was: queue time was 7.8 days, inspection time was 0.3 day, process time was 1.3 days, wait time was
Electralloy Ccorporation data for last month was: queue time was 7.8 days, inspection time was 0.3 day, process time was 1.3 days, wait time was 9.7 days, and move time was 0.7 day. Required: a. Compute the throughput time. b. Compute the manufacturing cycle efficiency (MCE). c. What percentage of the production time is spent in non-value-added activities? d. Compute the delivery cycle time