Question: Electrical work on a project cannot start until all of the electrical supplies have arrived on site. The relationship between the acquisition of all supplies
Electrical work on a project cannot start until all of the electrical supplies have arrived on site. The relationship between the acquisition of all supplies and the electrical work is: Finish-Start Start-Finish Finish-Finish Start-Start