Question: Electricians are the flow unit in a machine paced process with two sequential resources. The capacities of the resources are 0.026 and 0.027 electricians per
Electricians are the flow unit in a machine paced process with two sequential resources. The capacities of the resources are 0.026 and 0.027 electricians per hour. Demand occurs at the rate 0.03 electricians per hour.
What is the utilization (%) of the second resource?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts