Question: Electricians are trained in a process with two resources. The processing times for the resources are 21 and 85 hours, respectively. The first resource has

Electricians are trained in a process with two

Electricians are trained in a process with two resources. The processing times for the resources are 21 and 85 hours, respectively. The first resource has 3 workers and the second resource has 8 workers. Demand occurs at the rate 0.072 electricians per hour. Instruction: Round your answer to one decimal place. What is the utilization (%) of the first resource? %