Question: Emergency help needed!! Thank you! Correct answer please 12. The project's CPI at the end of period 8 is .......... a. 0.73 b. 0.69 c.
Emergency help needed!! Thank you! Correct answer please


12. The project's CPI at the end of period 8 is ..........
a. 0.73
b. 0.69
c. 1.25
d. 1.36
e. 1.11
13. The project's SV at the end of period 8 is ..........
a. 11
b. 17
c. -16
d. 19
e. -17
14. The project's CV at the end of period 8 is ..........
a. -6
b. 18
c. -17
d. 7
e. 12
15. The project's EAC at the end of period 8 is ...........
*Assume the future work will be accomplished to cover the performance gap. It means the CPI will not be the same*
a. 214
b. 169
c. 208
d. 481
e. 265
16. The project's EAC at the end of period 6 is ...........
*Assume the future work will be accomplished to cover the performance gap. It means the CPI will not be the same*
a. 298
b. 314
c. 369
d. 257
e. 148
Project EVM data The following data have been collected for a management information system project. 5 13 15 19 Task Weekly Cost B G 2 2 0 0 A 8 15 15 4 19 B + C 0 5 11 11 15 D C E 0 0 0 0 E 5 6 11 11 4 15 9 9 17 F 2 2 11 8 19 A 0 0 5 7 5 0 5 5 2 7 D 4 2 11 19 H 0 19 4 23 0 23 5555N ++ 5555N 257 ++ T 1585 5 5 5 5 10 10 10 10 F 10 10 10 10 G 5 5 5 5 H 10 10 5 5 ++ 153 1 +18 5 5 5 2 5 5 5 5 Earned Value Management Table % Complete EV AC A Finish 10 B 25% 15 C 33% 12 D 0% 0 Cumulative Totals 37 Period 8 Task % Complete AC A Finish 10 B 30% 20 C 60% 25 D 0% 0 Cumulative Totals 55 Answer the following questions regarding the project performance assessment. Period 6 EVM EV PV PVStep by Step Solution