Question: Emergency help needed!! Thank you! Correct answer please 9. What is the value of Y? (7 Marks) a. 6 b. 3 c. 2 d. 4
Emergency help needed!! Thank you! Correct answer please

9. What is the value of "Y"? (7 Marks)
a. 6
b. 3
c. 2
d. 4
e. 5
10. What is the value of "G"? ( 7marks)
a. 19
b. 12
c. 17
d. 11
e. 18
11. What is the value of "A"? ( 7marks)
a. 10
b. 8
c. 7
d. 11
e. 9
Consider the below project network diagram with lags. Lag 3 Task Task 2 3 withlag 7 Lag 5 A C D W Task 3 X Task 6 -> Lag 3 3 H G F 2 Lag 4 Task 4 Z Task 7 Lag 4 1 J 2 Answer the following questions regarding Early Start, Early Finish, Late Start, Late Finish, and Slack values. Y B Task 5 2 Lag 2 E Task 8 1