Question: Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadine. She has caiculated the crash cost

Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadine. She has caiculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?
A. Find the activity with the lowest crash cost
B.Calculate the optimum cost-time point
C.Calculate the crash point
D.Identify the critical path
E.Find the activity with the highest crash cost