Question: Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadine. She has caiculated the crash cost
Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadine. She has caiculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?
A Find the activity with the lowest crash cost
BCalculate the optimum costtime point
CCalculate the crash point
DIdentify the critical path
EFind the activity with the highest crash cost