Question: When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known.

When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?

Find the activity with the lowest crash cost

Calculate the optimum cost-time point

Calculate the crash point

Calculate indirect cost per time unit

Find the activity with the steepest cost slope