Question: When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known.
When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?
Find the activity with the lowest crash cost
Calculate the optimum cost-time point
Calculate the crash point
Calculate indirect cost per time unit
Find the activity with the steepest cost slope