Question: Emily works as a program manager for a software management company. Her work is mainly associated with Microsoft Project. She has begun a task named

Emily works as a program manager for a software management company. Her work is mainly associated with Microsoft Project. She has begun a task named Integration testing. When the task is only 25% complete, she wants to begin another task named Implementation. Which of the following options will she use to accomplish this? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Lead time option B Elapsed time option C Lag time option D Business time