Question: End item Z is assembled using three subassemblies: B, C and D. B is assembled using 2 Es and 2 Fs; C is made of
End item Z is assembled using three subassemblies: B, C and D. B is assembled using 2 Es and 2 Fs; C is made of 2 Gs and 2 Hs; and D is made of 3 Gs. On-hand inventories are 20 Cs, 20 Ds, and 200 Gs. Scheduled receipts are 20 Cs at the start of week 4, 30 Ds at the start of week 6, and 100 Gs at the start of week 3. 150 Zs will be shipped at the start of week 5, and another 150 at the start of week 7. Lead times are two weeks for subassemblies and one week for components E, F, G and H. Final assembly of Z requires one week. The manager instructed to make an extra of 10 percent scrap allowance in each planned order of G. Develop each of the following