Question: Engine Estimated labor time ( days ) Due date ( days ) A 5 8 B 4 1 5 C 1 0 1 2 D

Engine Estimated labor time (days) Due date (days)
A 58
B 415
C 1012
D 120
E 310
F 715
Develop schedules using SPT and EDD rules (5 point per each)
b.Obtain average job flow time, makespan, average earliness, average tardiness and average WIP inventory engines. (3 point per each)