Question: Q1. Create a schedule using the following priority-sequencing rules. Also, calculate the average days past due and flow time for each case. (Total points =

Q1. Create a schedule using the following priority-sequencing rules. Also, calculate the average days past due and flow time for each case. (Total points = 15 )

Order

Time since order arrived (days ago)

Estimated processing time (days)

Due date (days from now)

A

6

10

12

B

5

3

8

C

3

15

18

D

1

9

20

E

0

7

21

Case I: First-come, first-serve (FCFS) rule

Sequence of orders: __________________________________________ (1 point)

Order

Start time (days)

Processing time (days)

Finish time (days)

Due date

Days past due

Days ago since order arrived

Flow time (days)

Case II: Earliest due date (EDD) rule

Sequence of orders: _________________________________________ (1 point)

Order

Start time (days)

Processing time (days)

Finish time (days)

Due date

Days past due

Days ago since order arrived

Flow time (days)

Case III: Shortest processing time (SPT) rule

Sequence of orders: _________________________________________ (1 point)

Order

Start time (days)

Processing time (days)

Finish time (days)

Due date

Days past due

Days ago since order arrived

Flow time (days)

Finally,

Rule

Average days past due

Average flow time

FCFS

EDD

SPT

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!