Question: Q1. Create a schedule using the following priority-sequencing rules. Also, calculate the average days past due and flow time for each case. (Total points =
Q1. Create a schedule using the following priority-sequencing rules. Also, calculate the average days past due and flow time for each case. (Total points = 15 )
| Order | Time since order arrived (days ago) | Estimated processing time (days) | Due date (days from now) |
| A | 6 | 10 | 12 |
| B | 5 | 3 | 8 |
| C | 3 | 15 | 18 |
| D | 1 | 9 | 20 |
| E | 0 | 7 | 21 |
Case I: First-come, first-serve (FCFS) rule
Sequence of orders: __________________________________________ (1 point)
| Order | Start time (days) | Processing time (days) | Finish time (days) | Due date | Days past due | Days ago since order arrived | Flow time (days) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Case II: Earliest due date (EDD) rule
Sequence of orders: _________________________________________ (1 point)
| Order | Start time (days) | Processing time (days) | Finish time (days) | Due date | Days past due | Days ago since order arrived | Flow time (days) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Case III: Shortest processing time (SPT) rule
Sequence of orders: _________________________________________ (1 point)
| Order | Start time (days) | Processing time (days) | Finish time (days) | Due date | Days past due | Days ago since order arrived | Flow time (days) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Finally,
| Rule | Average days past due | Average flow time |
|
FCFS |
|
|
|
EDD |
|
|
|
SPT |
|
|