Question: Engineer Fatima and Cal Client executed a contract that included a provision that Cal could not file a lawsuit for professional negligence against Fatima after

Engineer Fatima and Cal Client executed a contract that included a provision that
Cal could not file a lawsuit for professional negligence against Fatima after two
years from the date of Building Department's final inspection of Cal's three-story
redwood decking, stairs and cover. The contract provision used for this particular
agreement is referred to as:
Condition Precedent
Single Condition
Condition Subsequent
Expressed Condition