Question: Engineering Economy class Qb/4 Please show the solution M4. Choose the correct set up from the four choices given to evaluate X from the given
Engineering Economy class
Qb/4
Please show the solution
M4. Choose the correct set up from the four choices given to evaluate X from the given cash flow diagram. Use an interest rate of 4% A. X= { 10,000-1,000( P/A, 4%, 6) + 100(P/G, 4%, 6)) (P/F, 4%, 6) B. X= { 10,000-1,000( P/A, 4%, 5) + 100( P/G, 4%, 5)) (F/P, 4%, 6) C. X= { 10,000-1,000( P/A, 4%, 6) + 100(P/G, 4%, 6)) (F/P, 4%, 6) D. X, 10,000-1,000(P/A, 4%, 6) + 100( P/G, 4%, 5)) (P/F, 4%, 6) S10K $700 $600 s800 $900 $1,000