Question: Engineering ecoonomics PRESENT ECONOMY STUDIES 1)A job in the completion stage can be completed in 40 days of 8hrs work per day with 40 men
Engineering ecoonomics
PRESENT ECONOMY STUDIES
1)A job in the completion stage can be completed in 40 days of 8hrs work per day with 40 men working with the contract expiring in 30 days, the engr. decided to add 10 more men, overtime not permitted. If the liquidated damages is P2k per day of delay, and the men are paid P400 a day, will the contractor be able to complete the job on time? Would he save money by adding more men?