Question: Enter the ES , EF , LS , LF , and Slack for each activity. ( Every box must be filled in so use 0

Enter the ES, EF, LS, LF, and Slack for each activity. (Every box must be filled in so use 0's if needed.)
ActivityESEFLSLFSlack1-21-31-42-52-63-74-75-86-87-8
Question 3b and 3c
The critical path is .
The expected duration is days.
Question 3d(Uncheck every box to remove the question mark and then check all that apply.)
If the project must be reduced by 3 days, the activites most likely affected are