Question: Erika is a project manager. She lists the project tasks and places them in the correct sequence. To build the project schedule, what is her

Erika is a project manager. She lists the project tasks and places them in the correct sequence. To build the project schedule, what is her next step?

1. Calculate the resources required for all summary tasks

2. Assign resources to all work packages

3. Add contingency buffers to the milestones

4. Include dependencies for all tasks