Question: Fatima is a project manager. She lists the project tasks and places them in the correct sequence. To build the project schedule, what is her
Fatima is a project manager. She lists the project tasks and places them in the correct sequence. To build the project schedule, what is her next step?
A
Include dependencies for all tasks.
B
Calculate the resources required for all summary tasks.
C
Add contingency buffers to the milestones.
D
Assign resources to all work packages.