Question: es 10 Question 17 n Completion Status: Activity A B C D E ANSWERS: MA Duration 7 2 6 7 5 6. What is

es 10 Question 17 n Completion Status: Activity A B C D E ANSWERS: MA Duration 7 2 6 7 5 6. What is the total cost for activity A 7. What is the total cost for activity C 8. What is the total cost for activity E n Precedence ww B B nds. QUESTIONS: 1. What is the duration of this project if executed without resource levelling? 2. What is the critical path for this project? (only write the number, no spaces, i.e. "ABCD") 3. What is the total resource needed to complete this project? S 4. If the labour histogram is drawn without any resource levelling, what would the peak resource need be? 5. During which week/weeks will the peak resource need be? (if there is only on week just write the week i.e. "1". If there are more than one weeks, only the week and a comma in between. i.e. "1,2". Resource Requirement per week hp 1 a 3 5 2 2 32 points 16C ^4) ENG 14:09 2021/09/01 Save Answer
Step by Step Solution
There are 3 Steps involved in it
What is the duration of this project if executed without resource levelling The duration of the project is 7 weeks Resource levelling is a process of ... View full answer
Get step-by-step solutions from verified subject matter experts