Question: ES Duration LS TASK EF Float LF LEGEND 9/12/2020 9/13/2020 9/14/2020 9:14 2020 B 919 2020 D 3 3 9/16/2020 9172020 9/17/2020 91/2020 9/11/2020 OS

ES Duration LS TASK EF Float LF LEGEND 9/12/2020

ES Duration LS TASK EF Float LF LEGEND 9/12/2020 9/13/2020 9/14/2020 9:14 2020 B 919 2020 D 3 3 9/16/2020 9172020 9/17/2020 91/2020 9/11/2020 OS 0 9/7/2020 9.11 2010 918/2020 1 9:13 911 2010 9.10.20 91/2020 9102020 1 E 9122020 E120201 9122020 91/2020 If Task starts two days late what is the effect on the project end date? (select the most appropriate answer) a. The project is two days late Ob There is no effect on the project end date c. The project is still two days early d. The project ends one day late