Question: Estimated Task Time Task ID Task Name Predecessor Cost / Day Total Cost 8 A Site Evaluation 150 1200 10 B Initial Design 200 2000
| Estimated Task Time | Task ID | Task Name | Predecessor | Cost / Day | Total Cost |
| 8 | A | Site Evaluation |
| 150 | 1200 |
| 10 | B | Initial Design |
| 200 | 2000 |
| 12 | C | Design Approval | A,B | 100 | 1200 |
| 5 | D | Order Materials | C | 300 | 1500 |
| 12 | E | Initiate Foundation Work | C | 80 | 960 |
| 14 | F | Design and Install Electrical | D | 60 | 840 |
| 8 | G | Design and Install Plumbing | D | 200 | 1600 |
| 6 | H | Design and Install HVAC | F,G | 300 | 1800 |
| 12 | I | Machine Installation | E,F | 120 | 1440 |
| 4 | J | Task Name | I, H | 150 | 600 |
Problem 3 - After Day 21 the following field report is provided. Determine and provide all metrics. In one or two sentences, what is your assessment of the project status based upon the metrics.
| Field Report Day 21 | ||
| Activity | % Complete | Incurred Cost |
| A | 100 | 1400 |
| B | 100 | 1900 |
| C | 100 | 300 |
| D | 20 | 800 |
| E | 50 | 500 |
| F | 0 |
|
| G | 0 |
|
| H | 0 |
|
| I | 0 |
|
| J | 0 |
|
Problem 4 - After Day 31 the following field report is provided. Determine and provide all metrics. In one or two sentences, what is your assessment of the project status based upon the metrics. Provide some easily identifiable scorecard for the status of this project.
| Field Report Day 31 | ||
| Activity | % Complete | Incurred Cost |
| A | 100 | 1400 |
| B | 100 | 1900 |
| C | 100 | 1400 |
| D | 100 | 1700 |
| E | 100 | 1100 |
| F | 50 | 400 |
| G | 50 | 750 |
| H | 0 |
|
| I | 0 |
|
| J | 0 |
|
Thank you!