Question: EV 8 - 2 Considering only the technical constraints and disregarding the resource constraints, which tasks are critical? Question 2 options: B , D and

EV8-2Considering only the technical constraints and disregarding the resource constraints, which tasks are critical?
Question 2 options:
B, D and F
A, B,D and F
B, D, E and F
A, B, C, D, E and F
Question 3(1 point)
Saved
Listen
What is the proper order for the heuristics used to prioritize activities when resources needed exceed the resources available?
Question 3 options:
123
Smallest duration
123
Minimum slack
123
Lowest identification number
Question 4(1 point)
Saved
Listen
Considering the resource constraints as well as the technical constraints, what is the shortest time that the project can be completed in?
Question 4 options:
10 time units
12 time units
14 time units
15 time units
Question 5(1 point)
Saved
Listen
Which tasks are critical after accounting for the resource constraints?
Question 5 options:
A, B, C, D, E and F
B, D and F
B, C, E and F
A, D and F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!