Question: EV analysis is an important tool to measure the performance of a project. It is a program management technique that uses work in progress to

EV analysis is an important tool to measure the performance of a project. It is a program management
technique that uses work in progress to indicate what will happen to the work in future. It compares
the actual work performed against a baseline plan. In this way, the analysis helps in setting a standard
for performance evaluation and controls the time and cost constraints. It also helps in identifying the
critical activities which maybe noted down and taken care of during further progress of the project
2.1 How can the project managers keep track of the possible areas that are prone to risk? (8)
2.2 Explain a strategic assessment, technical assessment, cost-benefit analysis and risk evaluation in
the process of project evaluation. (10)
2.3 Explain how to break the total project works and some major parts of the works into smaller and
manageable item. Relate your answer to project phases, costs, work package, activities, activity ID,
and WBS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!