Question: EVA EXERCISE FOR PRACTICE 2 A project has a budget of $100 000 and schedule for 10 weeks. It's assumed that the total budget will

 EVA EXERCISE FOR PRACTICE 2 A project has a budget of

EVA EXERCISE FOR PRACTICE 2 A project has a budget of $100 000 and schedule for 10 weeks. It's assumed that the total budget will be spent equally each week until the 10th week is reached. After 3 weeks the Profect Manager finds that only 10% of work is finished and atotal of the $40 000 spent. Find BAC, EV, AV, PV, CPI, SPI, Critical Ratio, Schedule Variance, Cost Variance, EAC, ETC and Total Project Time