Question: Evaluate the following project using an IRR criterion, based on an opportunity cost of 10%: C 0 = -6,000, C 1 = +3,300, C 2

Evaluate the following project using an IRR criterion, based on an opportunity cost of 10%: C0= -6,000, C1= +3,300, C2= +3,300.

a. Accept, since IRR exceeds opportunity cost.

b.Reject, since opportunity cost exceeds IRR.

c.Accept, since opportunity cost exceeds IRR.

d.Reject, since IRR exceeds opportunity cost.