Question: Evaluate the three statements below about project risks, and then choose the correct alternative: I - The primary questions project teams use in qualitative risk
Evaluate the three statements below about project risks, and then choose the correct alternative:
IThe primary questions project teams use in qualitative risk analysis are "how likely is this risk to happen?", and if it does happen, how big will the impact be IIOnce risks have been identified and analyzed, the project team decides how they will handle each risk.
IIIIn some cases, project teams will elect to reduce a threat to a level that a sponsor and other stakeholders deem acceptable, rather than eliminate it completely.
All statements are correct
Only statements I and II are correct.
Only statements I and III are correct.
Only statements II and III are correct.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock