Question: Evaluating the CPM network below, what effect would shortening Activity F and Activity B have on the overall completion time of the project? A. The
Evaluating the CPM network below, what effect would shortening Activity F and Activity B have on the overall completion time of the project?

A. The project would be extended by 5 days.
B. The project could be crashed by 8 days.
C. The project could be crashed by 5 days.
D. There would be no change in the completion time.
E. The new completion time would be 19 days.
B(5) C(6) A(7) G(3) D(6) E(4) (F(8)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
