Question: Evaluating the CPM network below, what effect would shortening Activity F and Activity B have on the overall completion time of the project? A. The

Evaluating the CPM network below, what effect would shortening Activity F and Activity B have on the overall completion time of the project?

Evaluating the CPM network below, what effect

A. The project would be extended by 5 days.

B. The project could be crashed by 8 days.

C. The project could be crashed by 5 days.

D. There would be no change in the completion time.

E. The new completion time would be 19 days.

B(5) C(6) A(7) G(3) D(6) E(4) (F(8)