Question: EX 1 3 - 2 ( Algo ) On day 5 1 a project has an earned value... On day 5 1 a project has

EX13-2(Algo) On day 51 a project has an earned value...
On day 51 a project has an earned value of $630, an actual cost of $560, and a planned cost of $620.
Compute the SV, CV, and CPI for the project. (Round your "CPI" answer to 2 decimal places.)