Question: EX 1 3 - 5 ( Algo ) Given the project network and baseline... Given the project network and baseline information below, complete the form
EXAlgo Given the project network and baseline...
Given the project network and baseline information below, complete the form to develop status reports for periods Report the
final SV CV CPI, and PCIB.
Do not round intermediate calculations. Enter all answers to decimal places. For SPI, CPI, and PCIB enter your answers as
decimals rather than percentage format eg enter instead of