Question: EX13-5 (Algo) Given the project network and baseline... Given the project network and baseline information below, complete the form to develop status reports for periods

 EX13-5 (Algo) Given the project network and baseline... Given the projectnetwork and baseline information below, complete the form to develop status reportsfor periods 1-4. Report the final SV, CV, CPI, and PCIB. 22 A 4 2 3 3 2 5 O 2 3 3

5 5 7 6 O O O 3 3 3 2 55 1 6 LEGEND ES ID EF O 3 2 2 65 O SL SL O 2 2 2 3 5 LS DURLFSchedule information Baseline budget needs ($000) ACT/ DUR ES LF SL Total

EX13-5 (Algo) Given the project network and baseline... Given the project network and baseline information below, complete the form to develop status reports for periods 1-4. Report the final SV, CV, CPI, and PCIB. 2 2 A 4 2 3 3 2 5 O 2 3 3 5 5 7 6 O O O 3 3 3 2 5 5 1 6 LEGEND ES ID EF O 3 2 2 6 5 O SL SL O 2 2 2 3 5 LS DUR LFSchedule information Baseline budget needs ($000) ACT/ DUR ES LF SL Total Time period WP PV O 2 3 4 5 6 2 3 12 4 8 2 3 0 3 O 15 3 7 5 3 2 0 2 O 8 4 4 4 2 2 5 6 3 3 5 2 3 5 O 10 6 A 6 3 2 5 O 9 3 3 3 7 1 5 6 O 5 5 Total PV by period 11 19 11 12 7 5 Cumulative PV by period 11 30 41 53 60 65 (Do not round intermediate calculations. Enter all answers to 2 decimal places. For SPI, CPI, and PCI-B, enter your answers as decimals rather than percentage format (e.g., enter 0.93 instead of 93%).)(Do not round intermediate calculations. Enter all answers to 2 decimal places. For SPI, CPI, and PCl-B, enter your answers as decimals rather than percentage format (e.g.. enter 0.93 instead of 93%).) Cumulative Totals Cumulative Totals End of Period 3 Task Actual % Complete EV AC PV CV SV 1 100 14.00 2 75 16.00 3 100 9.00 4 45 5.00 5 0 0.00 0.00 0.00 6 35 3.15 3.00 0.15 0.15 Cumulative Totals End of Period 4 Task Actual % Complete EV AC PV CV SV 1 100 14.00 2 100 19.00 3 100 9.00 4 100 10.00 5 30 4.00 6 70 6.30 8.00 (1.70) 7 0 0.00 0.00 0.00 Cumulative Totals

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!