Question: EX 8 - 9 ( Algo ) You have prepared the following schedule... You have prepared the following schedule for a project in which the
EXAlgo You have prepared the following schedule...
You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having
four backhoes. You recelve a call from your partner, Brooker, who desperately needs one of your backhoes.
You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in months. Develop a
resource schedule to see if it is possible to complete the project In months with only three backhoes.
The number of backhoes required by each activity is as shown In the diagram. No splitting of actlvitles is possible.
Use the following order of heurlstics: Minimum slack, Smallest duration, Lowest identlfication number
Schedule resource load chart with ES and slack updates
Note: Recall, in the schedule resource load chart the timeconstrained scheduling Interval ES through LF has been shaded. Any
resource scheduled beyond the shaded area will delay the project. TP stands for time period.
How long will the project take if only three backhoes are avallable?
List the order in which you scheduled the actlvitles of the resourceconstralned project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock