Question: EX 9 - 7 ( Static ) Use the information contained below... Use the following information to compress one time unit per move using the
EXStatic Use the information contained below...
Use the following information to compress one time unit per move using the leastcost method. Assume the total indirect cost for the project is $ and there is a savings of $ per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. What is the optimum costtime schedule for the project?
Note: The correct normal project duration and total direct cost are provided.
Activity Crash cost Maximum
ID Slope Crash Time Normal time Normal cost
A
B $
C
D
E
F
G
H
Total direct normal costs $
To compress from time period to time period crash the following activitys: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.
check all that apply
A
B
C
D
E
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock