Question: EX 9 - 7 ( Static ) Use the information contained below... Use the following information to compress one time unit per move using the

EX9-7(Static) Use the information contained below...
Use the following information to compress one time unit per move using the least-cost method. Assume the total indirect cost for the project is $2000 and there is a savings of $100 per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. What is the optimum cost-time schedule for the project?
Note: The correct normal project duration and total direct cost are provided.
Activity Crash cost Maximum
ID (Slope) Crash Time Normal time Normal cost
A 02200
B $50141,000
C 20025800
D 200251,000
E 10013800
F 40151,000
G 40141,000
H 01200
Total direct normal costs $6,000
To compress from time period 20 to time period 19 crash the following activity(s): (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
check all that apply 1
A
B
C
D
E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!