The objective of 'crashing' is to reduce the time of a project at an acceptable additional cost.
Fantastic news! We've Found the answer you've been seeking!
Question:
The objective of 'crashing' is to reduce the time of a project at an acceptable additional cost. For this assignment, determine all possible paths using the information contained in the chart. Compress one-time units per move using the least cost method. Assume the total indirect cost for the project is $700 and there is a savings of $50 per time unit reduced. Record the total direct, indirect, and project costs for each duration.
Show your work including your original options and any 'crashing' activity in detail.
Questions to answer:
- What is the optimum cost-time schedule for the project? (in units)
- What is the cost?