Question: EX13-3 (Algo) Given the project network and baseline... Given the project network and baseline information below, complete the form to develop a status report for

EX13-3 (Algo) Given the project network and baseline...

Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8

EX13-3 (Algo) Given the project network and

Time Period
Task DUR ES LF SL Budget (PV) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A 2 0 2 0 380 200 180
B 6 2 8 0 2300 200 500 200 600 200 600
C 5 2 9 2 1500 200 400 500 100 300
D 4 8 12 0 1610 410 400 400 400
E 3 7 12 2 1000 400 400 200
F 3 12 15 0 590 200 90 300
Period PV total 200 180 400 900 700 700 500 1,000 810 600 400 400 200 90 300
Cumulative PV total 200 380 780 1,680 2,380 3,080 3,580 4,580 5,390 5,990 6,390 6,790 6,990 7,080 7,380

(Do not round intermediate calculations. Round your table answer entries to the nearest whole number.)

EX13-3 (Algo) Given the project network and

LEGEND ESID EF SL SL 2 B 8 8 D 12 LS DUR LF 0 0 0 0 8 2 68 8 4 12 0A2 12 F 15 0 0 0 0 2 2 2 12 3 15 N C7 7 E 10 N 2 2 2 459 9 3 12 End of Period 4 Task AC Attual % Complete Finished 50 400 1,100 500 C 12 Solo 0 0 E 0 Cumulative Totals End of Period 8 Task EV AC PV CV SV Actual % Complete Finished Finished Finished 2.200 1,400 D E 0 0 Cumulative Totals

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!