Question: Example 1 : Assembly Line Balancing Given in the following table are the tasks necessary for the assembly of Fine Cedar Chests, the length of

Example 1: Assembly Line Balancing
Given in the following table are the tasks necessary for the assembly of Fine Cedar Chests, the length of time needed to perform each task, and the operations that must be completed prior to subsequent operations.
\table[[Element,Precedence,Time (min)],[A,None,2],[B,A,4],[C,B,5],[D,None,5],[E,D,3],[F,None,1],[G,F,2],[H,C, E, G,4]]
a) Calculate the cycle time necessary to complete 300 cedar chests in a 35-hour week.
b) What is the minimum number of workstations that can be used on the assembly line and still reach the production quota? Balance the line and calculate line's efficiency.
 Example 1: Assembly Line Balancing Given in the following table are

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!