Question: Example 2 : Assembly Line Balancing Given in the following table are the tasks necessary for the assembly of a particular product, the length of

Example 2: Assembly Line Balancing
Given in the following table are the tasks necessary for the assembly of a particular product, the length of time needed to perform each task, and the operations that must be completed prior to subsequent operations.
\table[[Task,Time (min),Precedence],[A,4,-],[B,2,A],[C,5,B],[D,5,B],[E,4,A],[F,3,C,D],[G,5,F],[H,2,E],[I,10,G,H]]
Calculate the cycle time necessary to complete 40 units of product in a day. Assume working time for a day is 400 minutes. Then balance the line and calculate line's efficiency.
 Example 2: Assembly Line Balancing Given in the following table are

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!