Question: Example 1 Bread Making on Two Lines Initial Assumptions The bakery sells only white bread. Two parallel baking lines, each equipped with a mixer, a
Example Bread Making on Two Lines
Initial Assumptions
The bakery sells only white bread.
Two parallel baking lines, each equipped
with a mixer, a proofer, and an oven.
The two baking lines share a single
packaging line.
hour work day
Which process is the bottleneck within each
baking line?
What is the bottleneck time of the st baking
line?
The nd
Figure Process Flow Diagram and Process Times for BreadMaking with Two Parallel Lines
Raw Process Time: Process Time: Process Time: Work in Finished
Materials hour hour hour Process Goods
loaves loaves loaves
Process Time:
hour
loaves
Process Time: Process Time: Process Time:
hour hour hour
loaves loaves loaves
Mix
Mix Proof Bake
BakeProof
Pack
What is the bottleneck time for the entire baking
line operation?
What is the bottleneck time for the entire bread
making process?
What is the throughput time for the entire bread
making process?
Figure Bottleneck Times for each BreadMaking Line
Raw
Materials Bottleneck Time: Work in Finished
hour loaves Process Goods
Process Time:
hour
loaves
Bottleneck Time:
hour loaves
Mix BakeProof
Pack
Mix BakeProof
How should the baking lines be scheduled
started together or staggered; run continuously
or with idle time
What is the overall daily capacity of the bread
making operation?
Figure Bottleneck Times for the Bakery
Raw Work in Finished
Materials Process Goods
Process Time:
hour
loaves
Bottleneck Time:
hour loaves
Bottleneck Time:
hour loaves
Mix BakeProof
Pack
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock