Question: Example 2 . 3 6 Given the following data in Table 2 . 1 1 4 , draw the CPM diagram, find out the critical
Example
Given the following data in Table draw the CPM diagram, find out the critical path and compute the total float, free float and independent floats for activities E D G H and L
MPRADCindd : AM
Chapter
Table Data on predecessor and duration for activities
Activity Predecessors Duration Days
A
B
C
D A
E C
F B C
G F
H D F
I E F K
J G H
K
L K
Solution:
The critical path is B~F~H~J and the duration is days. The floats for all the activities are given
in Table
Table Total, free and independent floats
Activity Predecessors Duration Days Total Float Free Float Independent Float
A
B
C
D A
E C
F B C
G F
H D F
I E F K
J G H
K
L K
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock