Question: Example 2 . 3 6 Given the following data in Table 2 . 1 1 4 , draw the CPM diagram, find out the critical

Example 2.36
Given the following data in Table 2.114, draw the CPM diagram, find out the critical path and compute the total float, free float and independent floats for activities E, D, G, H and L.
M02_PRAD30856_01_C02.indd 13706/02/1911:24 AM
138| Chapter 2
Table 2.114 Data on predecessor and duration for activities
Activity Predecessor(s) Duration (Days)
A 9
B 20
C 10
D A 11
E C 10
F B, C 4
G F 2
H D, F 5
I E, F, K 18
J G, H 14
K 24
L K 6
Solution:
The critical path is B~F~H~J and the duration is 43 days. The floats for all the activities are given
in Table 2.115.
Table 2.115 Total, free and independent floats
Activity Predecessor(s) Duration (Days) Total Float Free Float Independent Float
A 920
B 20
C 10555
D A 11220
E C 10544
F B, C 4
G F 2333
H D, F 5
I E, F, K 18110
J G, H 14
K 24130
L K 61313

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!